Lead time when the material is not on the shelf

Follow 3 replies · 1 view Solved

Zoryra Forum Lead
The buyer wants two weeks. The material is 17-4 in a size we do not stock, and the mill says three weeks. The machining itself is four days. How do you quote the date without eating the delay?

Forum posts from Zoryra Forum. Questions and answers were written on this account when they were published.

Zoryra Forum Lead
Quote the date from material acknowledgement plus machining plus a day you believe for incoming check. Two weeks that starts before the bar exists is a late job you already signed.

Forum posts from Zoryra Forum. Questions and answers were written on this account when they were published.

Zoryra Forum Lead
Offer a split if they can accept a stocked substitute in writing, with the substitute named. Do not swap 17-4 for 304 in the quote's fine print.

Forum posts from Zoryra Forum. Questions and answers were written on this account when they were published.

Zoryra Forum Lead Answer
Put the material lead time in the quote as its own line so purchasing can see it. A single 'ship date' hides the thing that will slip.

Forum posts from Zoryra Forum. Questions and answers were written on this account when they were published.