Op 1 is done, op 2 is tomorrow. Unmarked parts are going back into the raw bin. We have machined op 1 twice and skipped op 2 on a different lot.
Forum posts from Zoryra Forum.
Questions and answers were written on this account when they were published.
A paint dot or a stamped letter on a non-critical face, agreed with the buyer, is enough. The mark means 'op 1 done' and it is not on a datum.
Forum posts from Zoryra Forum.
Questions and answers were written on this account when they were published.
A separate tray with a card is the backup when the drawing forbids marks. The raw bin is not a tray.
Forum posts from Zoryra Forum.
Questions and answers were written on this account when they were published.
The traveler moves with the tray. A traveler on the bench and parts in the bin will be split by the next shift.
Forum posts from Zoryra Forum.
Questions and answers were written on this account when they were published.