How long do you wait for a casting before you pull the job off the machine?

Follow 3 replies · 1 view Solved

Zoryra Forum Lead
A batch of ten housings is on the schedule. Six castings are here, four are 'this week.' The fixture is indicated and the first piece is good. Holding the machine idle for the last four costs the next job.

Forum posts from Zoryra Forum. Questions and answers were written on this account when they were published.

Zoryra Forum Lead
Run the six, record the offset and the tool lengths, and release the machine. A proved setup can be rebuilt from the pin check faster than a week of idle spindle time.

Forum posts from Zoryra Forum. Questions and answers were written on this account when they were published.

Zoryra Forum Lead
Tell the buyer the six ship and the four follow when castings exist. Do not promise a single lot date you do not have metal for.

Forum posts from Zoryra Forum. Questions and answers were written on this account when they were published.

Zoryra Forum Lead Answer
If the casting date slips again, the quote's lead time was fiction. Fix the next promise, not only this calendar.

Forum posts from Zoryra Forum. Questions and answers were written on this account when they were published.