If we blast then anodize, how do the days stack?

Bead blast about +1–2 days; anodize about +2–4 days (hardcoat longer). They sit on production. Express ~6 days does not silently include every finish.

Public adders: bead blast about +1–2 days; anodize about +2–4 days, hardcoat longer. They add to production, not to duty. Call cosmetic faces, masks, and anodize type on the print or in notes.

Quantity 1 gets the same stack. Preview with no login. Complex parts: 12h UTC+8. Aluminum walls commonly ≥1.0 mm.

Lead time remains production + freight. Do not anodize stainless. No implants. Tick dimensional inspection separately.