Problem: EV Fixture Calendar Slips After Coating — Split the Clock

Problem: buyer plans a 10-day pilot for jigs / battery brackets, then powder or black oxide adds a silent week and the line trial slips.

Root cause: RFQ says “as soon as possible” without finish; the portal quote looked short because coating was not selected.

Fix: (1) Lock material grade + coating on day one. (2) Read production days and courier days as two lines. (3) Use Express only when blank + light finish allow.

Reference: blast +1–2d, powder +3–5d on the production clock — see Materials & finishes atlas.

Upload the fixture STEP on the quote page, pick the real finish, and share pilot qty + reorder rhythm with engineering.

AIkakumafɔlenEmail
PDF

Baara email de ka fisa ([email protected]). Mɔgɔ yɛrɛ ka batakiw bɛ OK. A bɛ se ka kɛ — telesarse bɛ baara kɛ hali bi.

An bɛna baara kɛ ni nin baara imɛri ye dɔrɔn walasa ka nin fɛn in ci ani k’i ka ɛntɛrinɛti ɲininkaliw jaabi (quote, lead time, drawings).

Problem: EV Fixture Calendar Slips After Coating — Split the Clock — Zoryra Precision