Problem: EV Fixture Calendar Slips After Coating — Split the Clock

Problem: buyer plans a 10-day pilot for jigs / battery brackets, then powder or black oxide adds a silent week and the line trial slips.

Root cause: RFQ says “as soon as possible” without finish; the portal quote looked short because coating was not selected.

Fix: (1) Lock material grade + coating on day one. (2) Read production days and courier days as two lines. (3) Use Express only when blank + light finish allow.

Reference: blast +1–2d, powder +3–5d on the production clock — see Materials & finishes atlas.

Upload the fixture STEP on the quote page, pick the real finish, and share pilot qty + reorder rhythm with engineering.

XigashadaAIEmail
PDF

Email-ka shaqada ayaa la doorbidayaa ([email protected]). Email-ka shaqsiga waa OK. Ikhtiyaari — soo dejintu weli waa shaqaynaysaa.

Waxaan u adeegsan doonaa email-kan shaqada kaliya si aan u soo dirno sheygan iyo inaan ka jawaabno su’aalahaaga injineernimada (qiimeyn, waqtiga hogaaminta, sawirro).

Problem: EV Fixture Calendar Slips After Coating — Split the Clock — Zoryra Precision