Fenitra mahazatra ~10 andro (prod + air sketch) · Haingam-pamokarana ~6 andro · sary / DFM

2026-08-10 · 4 min

Problem: Finish Adds a Silent Week — Masking Notes That Save Scrap

Problem: buyers pick “black anodize” late, then wonder why Standard ~10 days becomes ~14 — or threads seize after coating.

Fix: lock finish in the first quote; treat blast +1–2d, anodize +2–4d, powder +3–5d as production days (courier separate); mark masking on PDF.

Compatibility: anodize → aluminum; passivate → stainless; powder → check film vs fits.

Open Materials & finishes for the atlas, then configure the real finish on the quote page before you freeze the PO date.

Tenynalainatamin'nyAIEmail
PDF

Aleony mailaka momba ny asa ([email protected]). OK ihany koa ny mailaka manokana. Safidy — mbola miasa ihany ny fisintomana.

Hampiasa ity mailaka momba ny asa ity fotsiny izahay mba handefasana ity zavatra ity sy hamaliana ny fanontaniana momba ny injeniera (vidiny, fotoana mitarika, sarin-drafitra).

Problem: Finish Adds a Silent Week — Masking Notes That Save Scrap — Zoryra Precision