Problem: EV Fixture Calendar Slips After Coating — Split the Clock

Problem: buyer plans a 10-day pilot for jigs / battery brackets, then powder or black oxide adds a silent week and the line trial slips.

Root cause: RFQ says “as soon as possible” without finish; the portal quote looked short because coating was not selected.

Fix: (1) Lock material grade + coating on day one. (2) Read production days and courier days as two lines. (3) Use Express only when blank + light finish allow.

Reference: blast +1–2d, powder +3–5d on the production clock — see Materials & finishes atlas.

Upload the fixture STEP on the quote page, pick the real finish, and share pilot qty + reorder rhythm with engineering.

AIsitatEmail
PDF

Arbeiðs teldupostur er fyrimunur (navn@fyritøka.com). Persónligur postur er í lagi. Valfrítt — niðurtøkan virkar enn.

Vit brúka hendan arbeiðsteldupostin bert til at senda hendan lutin og til at svara tínum verkfrøðiligum spurningum (tilboð, leiðslutíð, tekningar).

Problem: EV Fixture Calendar Slips After Coating — Split the Clock — Zoryra Precision